Ideas and bugs about resource leveling
Benjamin Bayart <[email protected]> Fri, 10 Jan 2003 23:25:12 +0100
| Newsgroups | gmane.comp.gnome.apps.mr-project.devel |
|---|---|
| Message-ID | <[email protected]> |
Hi, I'm looking around about resource leveling on projects, and, as the current plugin is buggy, I'm searching some ideas... The current module is buggy in several ways: - it always try to move a task later, no earlier, which is rather logical if everything was planed "ASAP", but is wrong otherwise - it accepts to have the same resource allocated to two distinct tasks for one hour - you canot use your project anymore after using the module since all the time constraint have been altered. So, I was thinking about another way to do so... When I need to do it "by hand" I put a "predecessor" relationship between the two tasks (as the tasks are done by the same resource, one have to finish before the other). And I see no good reason not to do so like that in the automatic fashion, but that would require some "patchs" in the way MrProject handles things: 1. Creation a new kind of relation between tasks, or at least a flag "same resource" 2. Have another part, in the dialog box about resource displaying "task ordering", and alowing to swap two tasks (move up/move down) One would also need, then, to be able to have several tasks at the same time, if the resource is not overloaded (using units, and/or rate in the assignment). More over, from this task list, it's rather easy to obtain a time-table... I don't practice gtk at all, my first use of it was to build a small program to obtain timetables from mrproject, so I think I cannot try to write this stuff to test it, or at least not now. Do you all think I'm crazy, or is it, as I think, an interesting way? Thanks in advance for your ideas, Benjamin.