tor 2002-08-22 klockan 23.45 skrev Michele Ravani:
> On 22 Aug 2002 13:49:36 +0200 Mikael Hallendal <[email protected]> wrote:

> Well only partially. Think at a situation were your plan changes because of
> additional requirements and similar things. This wouldn't be captured by a
> baseline, but would by a versioning system.
> On the other hand, baselines could be pushed further. Instead of having a
> snapshot (i.e. the last saved baseline) a history could be stored, e.g.
> everytime the project is saved (ok, that's versioning) and one could start
> producing rather interesting graphs showing the progress vs plan over time
> of the project, of a group of tasks, etc. 

Ok, I've added an issue in the issue tracker so that we don't forget to
look at this when we are about to implement baselines:

http://bugzilla.codefactory.se/show_bug.cgi?id=257

Please add yourself to the CC-line if you are interested in tracking it
(you need an account in the bugzilla first).

> Yes, but your are storing (and entering) three values instead of two.
> If I say (and enter in the system as a parameter) that from my experience
> Joe Coder is within 20% of his estimates most of the times, I can use this
> information to get the likelyhood that a task will be delivered in time.
> If the work of Joe Coder depends on other tasks, this can be factored into
> the computation the same way. Worst case scenarios could be computed.
> One could even run MonteCarlo models on such a thing :o)

From what I understand those three values are needed for the PERT. I
guess they could be entered as you suggest. Perhaps in some way make it
optional which way you'd like to input it?
 
Regards,
  Mikael Hallendal

-- 
Mikael Hallendal                [email protected]
CodeFactory AB                  http://www.codefactory.se/
Office: +46 (0)8 587 583 05     Cell: +46 (0)709 718 918
lmpx.com only provides a reader for public news (NNTP) servers. It is not affiliated with the servers or forums shown here and is not responsible for the content of articles, which is written by their respective authors.