Re[4]: Feature suggestion: 2 times for "duration of task": optimistic and pessimistic
Michele Ravani <[email protected]>
| Newsgroups | gmane.comp.gnome.apps.mr-project.user |
|---|---|
| Message-ID | <[email protected]> |
On 23 Aug 2002 11:16:48 +0200 Mikael Hallendal <[email protected]> wrote: MH> From what I understand those three values are needed for the PERT. I MH> guess they could be entered as you suggest. Perhaps in some way make it MH> optional which way you'd like to input it? That would be a solution. There could be a problem mapping the short date and the long date to a standard deviation (and back) if they are not equidistant from the target date. However, i guess that in a first approximation a symmetric distribution, i.e. the probability of finishing early is the same as the one of finishing late (Ouch), could be enough. I guess that using dates kind of disturbs me. Assume that the target date is 15.9.2002 and that the earliest finishing date is 8.9.2002. With this information, you can only say that the chance that the task will be terminated on the 13.9.2002 is the same as the chance that it will be terminated at the 9.8.2002. This isn't realistic. Expressing the insecurity of the target date with essentially a probability distribution, i.e. a deviation, is a much more realistic statement: the chance of finishing 6 days early is much smaller than the one of finishing a day early. Anyway, it doesn't matter too much, as long as things can be expanded later. ciao -- Michele Ravani [email protected] "Those who live hoping, die singing" My Gran