Re: subtask(s) work counted wrong?
Karel Gardas <[email protected]>
| Newsgroups | gmane.comp.gnome.apps.mr-project.user |
|---|---|
| Message-ID | <Pine.LNX.4.43.0210011009410.971-100000@thinkpad.objectsecurity.cz> |
On Tue, 1 Oct 2002, Richard Hult wrote: > tis 2002-10-01 klockan 09.46 skrev Karel Gardas: > > Hello, > > > > I'd like to ask if it's really bug, but please look at mrproject user doc > > which is available on your web and list down to the Figure 2.17. A Task > > with subtasks. You can see here that task 1.1 takes 0 days even if its > > children takes 2 days in sum - t1.1.1 - 1 day and t1.1.2 - 1 day too. > > > > Is it a bug, or is my assumtion wrong? > > It's a bug that has been fixed in CVS, so the next released version will > work correctly. Thanks, unfortunately, I'm not able to compile current CVS. I'll send report about it in next email. BTW: Any timeframe when next version will be out? Thanks, Karel -- Karel Gardas [email protected] ObjectSecurity Ltd. http://www.objectsecurity.com