Re: start date of task

Jérôme Bouat <[email protected]>
Newsgroups gmane.comp.gnome.apps.mr-project.user
Message-ID <[email protected]>
Thanks.
I did not achieved it because I choosed
the 'edit task' entry in the contextual menu
on a task entry of the task list.
Is it a small 'features bug' ?

Jérôme

Le Vendredi 18 Octobre 2002 10:43, Richard Hult a écrit :
> tis 2002-10-15 klockan 17.51 skrev Jérôme Bouat:
> > How to define the start date of a task ?
>
> You could use the task view and set a "must start on" constraint on the
> task by clicking the start cell, selecting the right constraint type,
> and then choose your start date.
>
> Or, if you simply want to set the start date of the first task, you
> probably just want to set the start date of the project, which is done
> in the project properties dialog (which you can find in the File menu).
>
> Or, if you just want to make sure one task is put after another, you
> should create a dependency from the first task to the second. You do
> this in the Gantt view, by clicking on the first task and dragging to
> the second.
>
> Hope it helps,
> Richard