best practices

"David M. Cvet" <[email protected]>
Newsgroups gmane.comp.gnome.apps.mr-project.user
Message-ID <[email protected]>
> *Kirk Strauser * mrproject at lists.codefactory.se 
> <mailto:mrproject%20at%20lists.codefactory.se>
> /Tue Dec 10 17:42:00 2002/
>
>     * Previous message: [MrProject] posting Gantt charts on the web
>       <http://lists.codefactory.se/pipermail/mrproject/2002-December/001043.html>
>     * Next message: [MrProject] Build Problem for mrproject-0.7
>       <http://lists.codefactory.se/pipermail/mrproject/2002-December/001045.html>
>     * *Messages sorted by:* [ date ]
>       <http://lists.codefactory.se/pipermail/mrproject/2002-December/date.html#1044>
>       [ thread ]
>       <http://lists.codefactory.se/pipermail/mrproject/2002-December/thread.html#1044>
>       [ subject ]
>       <http://lists.codefactory.se/pipermail/mrproject/2002-December/subject.html#1044>
>       [ author ]
>       <http://lists.codefactory.se/pipermail/mrproject/2002-December/author.html#1044>
>
>
> ------------------------------------------------------------------------
>
>I want to start using MrProject for my scheduling needs, but I'm a little
>unclear about how to start.  For example, I'm an independent contractor, so
>I have quite a few clients, and I'm not sure whether I should be shoehorning
>all of the tasks into one big project file, or trying to coordinate them
>across several smaller ones.
>
>General:
>
>  Is it possible to give a set of default values system-wide?  For example,
>I'll also have the same resources available - namely, me and a couple of
>subcontractors.
>
I just started using mp0.7 and have found a similar constraint. 
Resources are not available system wide (I assume that to mean, across 
different project files).  

It would be extremely useful to have resources stored as an independent 
object so that one can import the resource pool into a new project, 
deleting what's not needed and adding new resources for that project. 
 At this time, resources are internalized into the same single project file.

A work around is to create a separate "project file" which only contains 
resources, i.e. resources.mrproject and use that as a template to create 
new projects (i.e. tasks are empty in this file) and populate the 
project with new tasks while having the resources already defined. 
 Remember to save the new project with a different name otherwise you'll 
hammer your "resources.mrproject" file.

>
>Time:
>
>  Is it possible to give projects a default time resolution of less than 1
>day?  Many of my tasks are in 15- or 30-minute blocks.  Can I configure
>MrProject to not display overnight hours by default?
>
Customization of mrproject essentially doesn't exist at this point. I'm 
sure it's on tap for the full version whenever it's ready.

>
>Cost:
>
>  How do you assign a cost to a task?
>
Can't assign cost to a task, but certainly to a resource.  I haven't 
tried to aggregate project costs at this point.  It would be useful to 
be able to cost out a project and achieve the granularity of costing out 
tasks too.

/dc

>
>
>In short, I know that this is a really flexible app, which can be a
>double-edged sword for new users.  :)
>-- 
>Kirk Strauser
>In Googlis non est, ergo non est.
>
>  
>

-- 
____________________________________________________________
David M. Cvet 
401-159 Frederick St., Toronto, Ont. Canada M5A 4P1
CELL:+1 416 726-8314  FAX:+1 416 366-7448
____________________________________________________________
lmpx.com only provides a reader for public news (NNTP) servers. It is not affiliated with the servers or forums shown here and is not responsible for the content of articles, which is written by their respective authors.