Resource overutilization
"Ben Pracht" <[email protected]> Tue, 25 Feb 2003 13:06:20 -0500
| Newsgroups | gmane.comp.gnome.apps.mr-project.user |
|---|---|
| Message-ID | <[email protected]> |
After reading the documentation, and searching the web site it seems that MrProject does not consider resource utilization. Consider this scenario: Project start date 1/1/2003 containing only two tasks: Task1 and Task 2. Task1 duration 10 days starting 1/1/2003 Task2 duration 20 days starting 1/1/2003 Person A for 100% on Task 1 Person A for 100% on Task 2 MrProject reports that the total time for Task1 and Task 2 is the maximum of the two tasks (20 days), instead of 30 days. This assumes that Task1 and Task2 can be done simultaneously. How can I get MrProject to either: tell me when a resource is overutilized, or move the start and end dates of a task to prevent the overutilization? Thanks in advance, Ben Pracht