Re: Task relationships working?
Richard Hult <[email protected]> 11 Mar 2003 16:12:58 +0100
| Newsgroups | gmane.comp.gnome.apps.mr-project.user |
|---|---|
| Organization | CodeFactory AB |
| Message-ID | <1047395577.2693.139.camel@sliff> |
tis 2003-03-11 klockan 15.55 skrev David McElvaney: > Overall: good job! you are real close to some systems like Fastrack > and Suretrack Thanks, nice to hear! > 1. I couldn't cause any relationship except FS 1day lag to actally > work. No matter what I selected in Edit Task, like SS with 40 days > lag, it displayed as FS with 1 day lag. Is this just something > non-obvious or a bug? Only FS is implemented for now. The lag field is a bit stupid, as it takes a time value in hours. I'm planning to make it work like the other time fields, where you can enter days or weeks or hours, etc. Regards, Richard -- Richard Hult [email protected] CodeFactory AB http://www.codefactory.se/