'Work'-field for tasks keep increasing...
Allan Beaufour Larsen <[email protected]> 22 Apr 2003 23:04:39 +0200
| Newsgroups | gmane.comp.gnome.apps.mr-project.user |
|---|---|
| Message-ID | <[email protected]> |
I have just created a new project, and it seems to work fine except for one thing: Every time I enter a value in a work-field it gets increased when I leave it. That is: If I enter '2d 9t' it ends up being '3d', and '3d' ends up being '3d 1t'. It also increases if I doubleclick the field (or print). Weird, and extremely annoying... It seems like the error is provoked by the fact that I changed the hours of a working day. I changed the working days to go from '9:00-12:00' and '12:40-20:00'. If I change them back, it works fine. Do you by any chance have some (hidden) expectations for how long a working day is? Regards, -- Allan Beaufour Larsen <[email protected]>