Re: Resourcing

Jos Vos <[email protected]> Wed, 21 May 2003 11:58:43 +0200
Newsgroups gmane.comp.gnome.apps.mr-project.user
Message-ID <[email protected]>
> [...] I want the answer to the opposite 
> question 'How can I stop mrproject scheduling the same person for two 
> tasks at once'.
> 
> In other words, if I create two tasks and assign the same person 
> (resource) to work on both of them, is there a way to force mrproject to 
> schedule the tasks one after the other, rather than at the same time?
> 
> I know I can manually do this by linking them. But if the two tasks are 
> really independent, until I assign resources they should be scheduled at 
> the same time. As soon as I assign the same resource to both of them, 
> they should be scheduled one after the other, as the same resource can't 
> do two things at once. Or at least THIS resource can't.

This is exactly what prohibits me from using MrProject in real life
now.  I don't even understand how people can live without this feature...

-- 
--    Jos Vos <[email protected]>
--    X/OS Experts in Open Systems BV   |   Phone: +31 20 6938364
--    Amsterdam, The Netherlands        |     Fax: +31 20 6948204