Re: Resourcing
Jos Vos <[email protected]> Wed, 21 May 2003 11:58:43 +0200
| Newsgroups | gmane.comp.gnome.apps.mr-project.user |
|---|---|
| Message-ID | <[email protected]> |
> [...] I want the answer to the opposite > question 'How can I stop mrproject scheduling the same person for two > tasks at once'. > > In other words, if I create two tasks and assign the same person > (resource) to work on both of them, is there a way to force mrproject to > schedule the tasks one after the other, rather than at the same time? > > I know I can manually do this by linking them. But if the two tasks are > really independent, until I assign resources they should be scheduled at > the same time. As soon as I assign the same resource to both of them, > they should be scheduled one after the other, as the same resource can't > do two things at once. Or at least THIS resource can't. This is exactly what prohibits me from using MrProject in real life now. I don't even understand how people can live without this feature... -- -- Jos Vos <[email protected]> -- X/OS Experts in Open Systems BV | Phone: +31 20 6938364 -- Amsterdam, The Netherlands | Fax: +31 20 6948204