Re: Weekends
Richard Hult <[email protected]> 02 Jun 2003 11:31:27 +0200
| Newsgroups | gmane.comp.gnome.apps.mr-project.user |
|---|---|
| Organization | CodeFactory AB |
| Message-ID | <[email protected]> |
fre 2003-05-30 klockan 15.35 skrev chuck: > I've upgraded to 0.9 and need to make weekends > workable. I set the calendar so every day is > a work day, the time to 0000-2359. Did you edit the default week to make Sat and Sun work days? It works here... You need to edit the default week for the calendar that you're using for the project, and then set the working time for that calendar as well. Regards, Richard