Re: Task default start date
Richard Hult <[email protected]> 02 Jun 2003 11:34:07 +0200
| Newsgroups | gmane.comp.gnome.apps.mr-project.user |
|---|---|
| Organization | CodeFactory AB |
| Message-ID | <[email protected]> |
fre 2003-05-30 klockan 05.43 skrev Ben Lau: > Hi all, > > I am using Mrproject 0.9.1. I got a problem in updating task list. > When i insert a new task in the mrproject, the task start date are > default set to the project start date. But i perfer to set the task > start date to today. Do it have method to change the default task start > day to today? Tasks are scheduled automatically in an "as-soon-as-possible" manner. If there are no dependencies or constraints set on the task, as soon as possible equals the start date. Try adding dependencies or set a constraint (in the task view, click the start date cell and choose a date and constraint type). Regards, Richard