Costs are not ok
Marco Biagiotti <[email protected]> Fri, 18 Jul 2003 16:29:06 +0200
| Newsgroups | gmane.comp.gnome.apps.mr-project.user |
|---|---|
| Message-ID | <[email protected]> |
Hello everybody! I set a new project with this datas: * RESOURCES - Name: Me - Type: Work - Cost: 10 * TASK - Name: Working - Start: 21 Jul - Stop: 22 Jul - Time: 2d - Cost: 60 - Resource: Me / Units 100 Working day is 8 h long so "Me" will work for 16h. In this case cost should be 160 (16h x 10 of cost)... why is it just 60? Thanks