Costs are not ok

Marco Biagiotti <[email protected]> Fri, 18 Jul 2003 16:29:06 +0200
Newsgroups gmane.comp.gnome.apps.mr-project.user
Message-ID <[email protected]>
Hello everybody!

I set a new project with this datas:

* RESOURCES
- Name: Me
- Type: Work
- Cost: 10

* TASK
- Name: Working
- Start: 21 Jul
- Stop: 22 Jul
- Time: 2d
- Cost: 60
- Resource: Me / Units 100

Working day is 8 h long so "Me" will work for 16h.

In this case cost should be 160 (16h x 10 of cost)... why is it just 60?

Thanks