In GANTT chart view, drag a predecessor towards the other task you want done next to the first. Or right-click the task in the Tasks view, choose Edit tast from popup and go to the "Predecessors" tab page. mv Giuseppe Sacco kirjutas E, 25.08.2003 kell 13:30: > Hi, > I am using MrProject for the first time and I have a problem about > serializing tasks: I have many tasks that should be accomplished by the > same person and, of course, these tasks should be serialized. I do not > have any preference about the order of these activities, so that any > order is good. I do need the serialization since I need an estimation of > the duration af the project. > > Actually MrProject let all activities start the first day of the project > but that person will not be able to do all of that at the same time :-) > > How do I set this kind of things in MrProject? > > Version information: mrproject 0.9.1 on Debian/powerpc "testing". > > I thank you very much, > Giuseppe Sacco > > _______________________________________________ > MrProject mailing list > [email protected] > http://lists.codefactory.se/cgi-bin/mailman/listinfo/mrproject