Re: question about serializing task

Margus Väli <[email protected]> 25 Aug 2003 14:10:19 +0300
Newsgroups gmane.comp.gnome.apps.mr-project.user
Message-ID <1061809819.32431.5.camel@oracle>
In GANTT chart view, drag a predecessor towards the other task
you want done next to the first. Or right-click the task in the
Tasks view, choose Edit tast from popup and go to the "Predecessors"
tab page.

mv

Giuseppe Sacco kirjutas E, 25.08.2003 kell 13:30:
> Hi,
> I am using MrProject for the first time and I have a problem about
> serializing tasks: I have many tasks that should be accomplished by the
> same person and, of course, these tasks should be serialized. I do not
> have any preference about the order of these activities, so that any
> order is good. I do need the serialization since I need an estimation of
> the duration af the project.
> 
> Actually MrProject let all activities start the first day of the project
> but that person will not be able to do all of that at the same time :-)
> 
> How do I set this kind of things in MrProject?
> 
> Version information: mrproject 0.9.1 on Debian/powerpc "testing".
> 
> I thank you very much,
> Giuseppe Sacco
> 