How do we define "fixed duration"?
Maurice van der Pot <griffon26-bCGDfOjggl9Wk0Htik3J/[email protected]>
| Newsgroups | gmane.comp.gnome.apps.planner.devel |
|---|---|
| Message-ID | <[email protected]> |
I was looking at bug #486990: "fixed duration tasks have incorrect
duration."
What length should a fixed duration task get?
current implementation:
Should they run during the weekend? no
Should they run during general holidays? no
... during vacation of allocated resources? no
... during lunch time? no*
*) this is what the bug is about. A fixed duration task of 1 day
should not end 1 hour before the working day ends just because it
continues during lunch.
Regards,
Maurice.
P.S.: It looks weird to have a resource allocated for a fixed duration
task. The units will just be adjusted to make sure the duration stays
the same. Are these tasks generally used without resources allocated?
--
Maurice van der Pot
Gentoo Linux Developer [email protected] http://www.gentoo.org
Creator of BiteMe! griffon26-bCGDfOjggl9Wk0Htik3J/[email protected] http://www.kfk4ever.com
_______________________________________________
Planner-dev-list mailing list
[email protected]
http://mail.gnome.org/mailman/listinfo/planner-dev-list
signature.asc
(application/pgp-signature, 189 B)
-----BEGIN PGP SIGNATURE----- Version: GnuPG v2.0.7 (GNU/Linux) iD8DBQFHGhfcMGnpIbeahxwRAuttAJ9SDiew3URGfuk7dqGQUGur2G585wCaA56m Jt52PJvtx4t5YbpMciIaQIQ= =q4NT -----END PGP SIGNATURE-----