Re: How do we define "fixed duration"?
Sebastien Roy <Sebastien.Roy-UdXhSnd/[email protected]>
| Newsgroups | gmane.comp.gnome.apps.planner.devel |
|---|---|
| Organization | Sun Microsystems |
| Message-ID | <[email protected]> |
Maurice van der Pot wrote: > I've sent a mail to the submitter of the bug and this was his reply: Thanks for the summary, I wasn't on the list when I sent my reply. I am now. :-) > The way I see it we now already have 2 different situations: > > 1) a task that will go on no matter what (e.g. drying of paint). > It needs to continue during weekends, nights, etc. > > 2) an activity for which a certain amount of time is alotted. People > will be assigned to participate for a certain percentage of their > time (nr of units). > > We should take the number of hours in a day from the project > calendar. > > In this case we can calculate work to be the total sum of units spent > by all assigned resources during this period. If either the nr of > units for a resource or the duration is modified, we should > recalculate work. We should probably make work read-only (!). Yes, excellent summary. This is precisely my thinking as well. > Are there more types? Kurt, you suggested a task to be done during > curing of concrete, but isn't that more of a finish-to-finish > relationship between the work and the curing? > > What I'm looking for is a type of task for which duration & work have > been filled in by the user and for which units should be recalculated. > I'm hoping there is no such task. I'm not sure if this kind of task is that useful, given that you can enter in the amount of work in a regular task, and adjust resources to match your expectation of its duration... Of course, this assumes that we haven't read the Mythical Man Month. ;-) -Seb