Managing the triple constraints appropriately

"Anmar Oueja" <[email protected]>
Newsgroups gmane.comp.gnome.apps.planner.devel
Message-ID <[email protected]>
Hello Guys:
I have been playing with planner 0.14 and I noticed that we don't include
the efficiency/availability/utilization in our work and duration
calculations.  In other words, if I enter work to be 3 days, duration is
automatically 3 days.  This is correct if the utilization is 100% but that
is not always.  Many times people are working on two activities at once with
50% utilization for each.


                   Work
Duration = -------------------
                    Utilization

p.s. I am using Utilization but we can name is efficiency or availability.

I think this is a very fundamental for any PM tool that is planning on going
places.  Do you know if our engine handles such an issue.

Your thoughts pleas?

_______________________________________________
Planner-dev-list mailing list
[email protected]
http://mail.gnome.org/mailman/listinfo/planner-dev-list
lmpx.com only provides a reader for public news (NNTP) servers. It is not affiliated with the servers or forums shown here and is not responsible for the content of articles, which is written by their respective authors.