Managing the triple constraints appropriately
"Anmar Oueja" <[email protected]>
| Newsgroups | gmane.comp.gnome.apps.planner.devel |
|---|---|
| Message-ID | <[email protected]> |
Hello Guys:
I have been playing with planner 0.14 and I noticed that we don't include
the efficiency/availability/utilization in our work and duration
calculations. In other words, if I enter work to be 3 days, duration is
automatically 3 days. This is correct if the utilization is 100% but that
is not always. Many times people are working on two activities at once with
50% utilization for each.
Work
Duration = -------------------
Utilization
p.s. I am using Utilization but we can name is efficiency or availability.
I think this is a very fundamental for any PM tool that is planning on going
places. Do you know if our engine handles such an issue.
Your thoughts pleas?