a thought about automating resource allocation
"David Nicol" <[email protected]>
| Newsgroups | gmane.comp.gnome.apps.planner.devel |
|---|---|
| Message-ID | <[email protected]> |
while leafing through http://www.semistable.com/thesis.pdf I wondered about supporting two things I do not recall seeing in any planning software. But maybe I just wasn't paying attention. (1) different completion rates assigned to different resources, that is, a way to represent that while Greg would take two weeks to do something, it would take Pitr just one day (2) switching costs. Represent the hour that is lost when Pitr hands off his project to Sid before rescuing Greg. -- But some very large rats, Ate his coats and his hats, While that futile old gentleman dozed. http://cronos.advenge.com/pc/nonsense/nonsense27.html