missing calculation work day for html

[email protected] Sat, 25 Oct 2008 23:58:58 +0900
Newsgroups gmane.comp.gnome.apps.planner.devel
Message-ID <[email protected]>
Hello developers,

I found problem in html output.
i.e.
Set to start time 10:00 to 13:00 and 14:00 to 17:00 (6 hour of day)
Insert a task need in gantt WBS and set to 4 days work.
After that extend output with html
check work day is 3 days  instead of 4 days.

Sample is attached.

Thanks,

_______________________________________________
Planner-dev-list mailing list
[email protected]
http://mail.gnome.org/mailman/listinfo/planner-dev-list
Edit-Woking-Time-s.png (image/png, 7.5 KB) - not displayed
export-html-s.png (image/png, 19.7 KB) - not displayed
Gantt-task2-s.png (image/png, 12.5 KB) - not displayed