Addition of PERT functionalities to Planner + slip line.

Gabriel Camby <[email protected]> Sun, 14 Jun 2009 16:56:56 +0200
Newsgroups gmane.comp.gnome.apps.planner.devel
Message-ID <[email protected]>
Hello Planner developpers,

I'm Gabriel Camby. I started working on Planner since the beginning of this
year. I did a student project on Planner. This project consisted in adding
PERT features and slip line support in Planner.
This resulted in a patch, thanks to Maurice van der Pot.

I submitted this patch on Bugzilla adding features from the PERT analysis
and from project slippage analysis to Planner. (
http://bugzilla.gnome.org/show_bug.cgi?id=585731)

Here are the details:

This enhancement patch add some functionalities from the PERT analysis and
project slippage analysis to Planner.

The PERT functionalities are:
- addition of a PERT view to Planner containing a task tree and a PERT
diagram.
- display of a PERT diagram using automatic configuration of the display.
Two modes are available "critical tasks on top" and "tasks flow".
- addition of two displayable columns : slack time & free float.

The project slippage analysis functionality is the slip line. It contains:
- property of displaying the slip line or not in the Gantt view.
- display of a slip line on the Gantt chart when clicking on the header. A
click in the upper part displays a slip line at the choosen date with a
thick line. A click in the lower part displays a thin line.

Note: the print parts for those additions are not implemented.

Can it be merged in Planner or in a branch?
I'll be glad if you tell me what you think of it.

Regards,
Gabriel Camby.

_______________________________________________
Planner-dev-list mailing list
[email protected]
http://mail.gnome.org/mailman/listinfo/planner-dev-list