Re: Planner-list Base lining a task

amitst <[email protected]>
Newsgroups gmane.comp.gnome.apps.planner.user
Message-ID <[email protected]>

Kurt Maute wrote:
> 
> On Mon, 2009-03-02 at 20:37 -0800, amitst wrote:
>> I didn't find any feature in the Planner to base line the task so that if
>> I
>> have to again plan the task due to delays etc. the original plan is lost.
>> 
>> Can we have this feature in the Planner or is there any workaround to be
>> used for this?
> 
> This feature has been discussed before, but hasn't yet been implemented.
> http://bugzilla.gnome.org/show_bug.cgi?id=140676
> 
> I guess the only workaround for now is to save your baselined project
> plan and copy it to a new one before making any updates/revisions.
> 
> -- 
> Kurt Maute <[email protected]>
> 
> _______________________________________________
> Planner-list mailing list
> [email protected]
> http://mail.gnome.org/mailman/listinfo/planner-list
> 
> 

Thanks Kurt!

Also I wanted to know whether there is a way for updating the actual effort
of a task especially beyond the planned date. If I have planned the task for
say two days and in actual the task spills over to say four days then I want
to put actual effort for four days against the above task only. Is there a
way to do that (i.e. separation of planned effort and duration from the
actual effort and duration)?

Best,
Amit
-- 
View this message in context: http://www.nabble.com/Base-lining-a-task-tp22302405p22345000.html
Sent from the Gnome - Planner - User mailing list archive at Nabble.com.