Re: Planner-list marking subtasks as done

Alexandre Franke <[email protected]>
Newsgroups gmane.comp.gnome.apps.planner.user
Message-ID <[email protected]>
On Fri, Jun 26, 2009 at 5:24 PM, Marc Becker<[email protected]> wrote:
> Hi,

Hi,

> I'm trying to mark subtasks as done. Therefore I'm editing the subtask and
> set the percentage to 100%. After closing and reopening the percentage is
> always set to 75%.
> Can someone tell me what am I doing wrong?

You're not doing anything wrong, this a known bug:
http://bugzilla.gnome.org/show_bug.cgi?id=580216
It was introduced in version 0.14.4 and we don't know yet how to solve it.

-- 
Alexandre Franke