It is the percentage of time spent by the resource on the task. For
instance, if a task has a workload of 1h and I assign myself at 50%, I
will need 2h to get it done. If I'm not alone and another resource
works on it at 50% too, we'll get it done in 1h. The task duration
(tasks view) is calculated from that if it's not set as fixed.