Re: Planner-list ressource assignation: credits
Alexandre Franke <[email protected]>
| Newsgroups | gmane.comp.gnome.apps.planner.user |
|---|---|
| Message-ID | <[email protected]> |
On Tue, Sep 8, 2009 at 4:27 PM, Rakotomandimby Mihamina<[email protected]> wrote: > Hello, Hi, > What does the "unit" field mean in the assignation pop-up? > Is it equivalent to "implication"? It is the percentage of time spent by the resource on the task. For instance, if a task has a workload of 1h and I assign myself at 50%, I will need 2h to get it done. If I'm not alone and another resource works on it at 50% too, we'll get it done in 1h. The task duration (tasks view) is calculated from that if it's not set as fixed. > Thank you. You're welcome. -- Alexandre Franke