Re: Planner-list Short tasks

Alan Barclay <[email protected]>
Newsgroups gmane.comp.gnome.apps.planner.user
Message-ID <[email protected]>
'15min' is the same as 0.25h, the number appears to be accepted, but not
displayed, and double clicking on the blank widget causes the value to be
lost.

2009/9/14 Alexandre Franke <[email protected]>

> On Sun, Sep 13, 2009 at 2:37 AM, Alan Barclay <[email protected]>
> wrote:
> > My projects often have short tasks, for example 15 minutes.
> >
> > If I enter '15m', then it's treated as 15 days - obviously not right
>
> Try '15min' and let us know if that solves your problem :)
>
> --
> Alexandre Franke
> _______________________________________________
> Planner-list mailing list
> [email protected]
> http://mail.gnome.org/mailman/listinfo/planner-list
>

_______________________________________________
Planner-list mailing list
[email protected]
http://mail.gnome.org/mailman/listinfo/planner-list