Planner-list predecessors for fixed date tasks

pete davidson <[email protected]> Sat, 24 Oct 2009 21:42:32 -0700
Newsgroups gmane.comp.gnome.apps.planner.user
Message-ID <[email protected]>
Hi all

Apologies for what's probably a newbie question.

I'm trying to use Planner to manage academic grant applications.  As such,
there's a number of key tasks whose dates are externally set and
non-negotiable (such as the date the grant must be submitted to the funding
agency, or the date a letter of intent is due to the funding agency).  I've
been 'locking' these dates by creating a milestone task (eg "Submit grant")
with a schedule of 'on fixed date' on the required date.

The problem I'm having is when I try and link these milestone tasks to the
rest of the tasks in the project by setting a predecessor.  This produces
the error "You cannot add a relationship to a task with a Must Start On
constraint."  I've also tried using a one-day task instead of a milestone
task, but get the same error.

Is there another approach to dealing with externally set fixed dates that
I'm missing, or a way to set milestone tasks which allows linking to other
tasks?

Any suggestions would be most welcome.

Regards

Pete