Re: Planner-list noworking days
[email protected] Thu, 19 Nov 2009 18:52:19 +0100 (CET)
| Newsgroups | gmane.comp.gnome.apps.planner.user |
|---|---|
| Message-ID | <1150565158.125561258653139066.JavaMail.root@zimbra18-e3.priv.proxad.net> |
----- Mail Original ----- De: "Alexandre Franke" <[email protected]> À: [email protected] Envoyé: Mercredi 18 Novembre 2009 22h36:37 GMT +01:00 Amsterdam / Berlin / Berne / Rome / Stockholm / Vienne Objet: Re: Planner-list noworking days On Wed, Nov 18, 2009 at 6:34 PM, Maurice van der Pot <[email protected]> wrote: > On Tue, Nov 17, 2009 at 09:57:27PM +0100, [email protected] wrote: >> is it possible not to see noworking days in gantt view ? > > No, it is not possible to hide non-working days from the gantt view. Oops, sorry for my earlier answer, I had read "is it possible to see". -- Alexandre Franke hello again thank for you reply do you know if, in a future version, it will be possible to hide noworking days. vincent verilhac _______________________________________________ Planner-list mailing list [email protected] http://mail.gnome.org/mailman/listinfo/planner-list _______________________________________________ Planner-list mailing list [email protected] http://mail.gnome.org/mailman/listinfo/planner-list