Re: Planner-list Start As late as possible
Maurice van der Pot <griffon26-bCGDfOjggl9Wk0Htik3J/[email protected]> Tue, 26 Jan 2010 18:31:43 +0100
| Newsgroups | gmane.comp.gnome.apps.planner.user |
|---|---|
| Message-ID | <[email protected]> |
On Tue, Jan 26, 2010 at 02:51:47PM +0100, Yohann Monnier wrote: > Learning Critical Chain method, I am looking for a basic feature, > changing the schedule of a task to "As late as possible", But i did > not find where to do it. > > There is something about as early as possible or fixed, but not as > late as possible. > > Does someone know where to enable it on a task ? Then you will have to set a predecessor with a start-to-finish relationship. So if you have a milestone some time in the future: - double-click the task that should be done as late as possible before that milestone - go to the predecessor tab - add the milestone as predecessor with the relation type set to finish-to-start > Is it important to suscribe to the mailing list if i want to see your > answers ? I've replied to you directly, but you can keep an eye on http://mail.gnome.org/archives/planner-list/2010-January/thread.html for replies as well. Regards, Maurice. -- Maurice van der Pot Gentoo Linux Developer [email protected] http://www.gentoo.org Gnome Planner Developer griffon26-bCGDfOjggl9Wk0Htik3J/[email protected] http://live.gnome.org/Planner _______________________________________________ Planner-list mailing list [email protected] http://mail.gnome.org/mailman/listinfo/planner-list
signature.asc
(application/pgp-signature, 198 B)
-----BEGIN PGP SIGNATURE----- Version: GnuPG v2.0.13 (GNU/Linux) iEYEARECAAYFAktfJv8ACgkQMGnpIbeahxyu/gCeNmWs+BOWjwJyudwhWrExL9me F1MAnjkvoAW0/KMIv49O+Xf/xsjaUQR+ =yaZP -----END PGP SIGNATURE-----