Hello everyone, I am new to project management softwares on Ubuntu. Planner seems to be just what I need, except I really need to set a "relative" scheduling for some projects. I mean, the project could start whenever my administration accepts it and I don't now precisely when it is going to be! Then I have to produce for them a previsional scheduling with a start time "t0" and weeks numbering "week #1, week #2,..." and so on, instead of fixed, absolute dates. Hope I am clear :S Is there a way to do it with planner ? Thanks a lot!