Planner-list Dates / Working days
Randall Wright <[email protected]> Wed, 2 Feb 2011 12:36:27 -0800
| Newsgroups | gmane.comp.gnome.apps.planner.user |
|---|---|
| Message-ID | <[email protected]> |
I need a task to start Saturday and end Monday with Sunday not being counted. I am using Planner 0.14.3 on Fedora 14. I am having a problem with setting the working days. Some days I work Sat but mostly on weekdays. When I try to adjust a task so it starts on a Saturday, it automatically moves it to the following Monday. When I change the working dates in the calendar, it allows me to move it to a Friday that goes right through till Monday. Is there a way to set it up so it only does Sat through to Monday without using Friday to Monday? Thank you! Randall _______________________________________________ planner-list mailing list [email protected] http://mail.gnome.org/mailman/listinfo/planner-list