Re: Planner-list Dates / Working days

wayne <[email protected]> Thu, 03 Feb 2011 05:27:04 -0600
Newsgroups gmane.comp.gnome.apps.planner.user
Message-ID <[email protected]>
On 02/02/2011 02:36 PM, Randall Wright wrote:
> I need a task to start Saturday and end Monday with Sunday not being 
> counted.
>
> I am using Planner 0.14.3 on Fedora 14. I am having a problem with 
> setting the working days. Some days I work Sat but mostly on weekdays. 
> When I try to adjust a task so it starts on a Saturday, 
> it automatically moves it to the following Monday. When I change the 
> working dates in the calendar, it allows me to move it to a Friday 
> that goes right through till Monday. Is there a way to set it up so it 
> only does Sat through to Monday without using Friday to Monday?
>
> Thank you!
> Randall
>
>
> _______________________________________________
> planner-list mailing list
> [email protected]
> http://mail.gnome.org/mailman/listinfo/planner-list
You must click on the "Project" tab, then on "Manage Calendar" and then 
click "Default Week" tab change "Saturday" from non-working to working.  
Save your changes before exiting.

-- 
Wayne D Hammond
La Porte, Texas