Re: Planner-list Irregular vacation dates
Alexandre Franke <[email protected]> Thu, 17 Feb 2011 16:49:19 +0100
| Newsgroups | gmane.comp.gnome.apps.planner.user |
|---|---|
| Message-ID | <[email protected]> |
On Thu, Feb 17, 2011 at 3:09 PM, fox <[email protected]> wrote: > Hi, Hi. > Is there a way to have irregular vacation dates for resources? If yes, > do they remove the resource from a tasks completion time calculation? Yes. In resource view, edit rescource, go to calendar tab, edit calendars and simply set vacation days as non-working days for the calendar you'll assign to this resource. P.S.: you should subscribe to the mailing list if you want to get answers for your questions. I had to manually accept your mail as posts from non-subscribed people are moderated. -- Alexandre Franke