Re: Planner-list how to assign a fixed cost to a task

Alexandre Franke <[email protected]> Sun, 10 Apr 2011 13:28:49 +0200
Newsgroups gmane.comp.gnome.apps.planner.user
Message-ID <[email protected]>
On Sat, Apr 9, 2011 at 3:15 PM, jolyon tidmarsh <[email protected]> wrote:
> Hello,

Hi,

If you want to see replies to your mail, make sure you subscribe to
the list. Your mail got in moderation queue and someone had to
manually approve it because you're not subscribed.

> I'm new to Planner and am struggling to assign a fixed cost to a task.

I'm pretty sure this is not supported at the moment. I thought there
was a feature request for that but I couldn't find it on bugzilla.

>  The 'material' resource cost that I've assigned seems to scale with the
> number of days.

See https://bugzilla.gnome.org/show_bug.cgi?id=306979

> I'm also struggling to find any on-line help - can you point me at any
> forums? (or is it fora?)

We don't have any forum. People usually use this list or sometimes the
IRC channel (#planner on irc.gnome.org), although you'll have to be
patient since people might take time to see your question and answer
it.

-- 
Alexandre Franke
_______________________________________________
planner-list mailing list
[email protected]
http://mail.gnome.org/mailman/listinfo/planner-list