Hi,

I'm new to Gnome Planner. Everything's great so far, but I have a couple of
questions.


1. I'd like to make it so that when I insert a new task the default Schedule
is "On fixed date" (and have the default date be "Today") rather than "As
soon as possible". Is there a way to do this?


2. Is there a way to make the entries in the "% Complete" column automatic,
for tasks that have subtasks? This should take duration of subtasks into
account.

For example, suppose my tasks were:

Project  6d
   A       1d
   B       2d
   C       3d

and suppose tasks A, B, and C were, respectively, 100%, 40%, and 50%
complete. Then the whole Project task should be

( 1.00 * 1d + 0.40 * 2d + 0.50 * 3d ) / 6d   *  100 %  =  3.3d / 6d  *  100
%  =  55 % complete.

It would be nice if this were computed automatically. Is this feature
present, and if so how do I activate it?


Thanks. :)

Steve Kieffer