Planner-list Project resource only on specific days
"Andre Rothe" <arothe-4jPSrHq1eo/[email protected]> Tue, 25 Oct 2011 13:15:39 +0200
| Newsgroups | gmane.comp.gnome.apps.planner.user |
|---|---|
| Message-ID | <[email protected]> |
Hi, I try to define my current project with Planner. The project has different tasks, which have specific lengths. But the resource (me) can only work on some days of the week (Thuesday, Thursday, Friday) on the project. What I need is a plan, whether or not I'm out of the plan. The first task needs four days, but if I start on 24th of October it must not be done on 27. of October (because I work on it on 25., 27., 28. and 31. of October only). So the task ends in time on 31. of October. How can I configure that without manually re-calculated task times? Thanks a lot Andre