Re: Planner-list start date for HTML export
Alexandre Franke <[email protected]> Fri, 20 Jan 2012 16:14:25 +0100
| Newsgroups | gmane.comp.gnome.apps.planner.user |
|---|---|
| Message-ID | <CAJ-e=JDF2AEFqPsRiyD847nUVncPn+Bu9SGav21Oooyw8ckPMg@mail.gmail.com> |
2012/1/20 Jérôme VÉRITÉ <[email protected]>: > Hi, Bonjour, > I try to export a project to the HTML view with a specified start date in > the project properties but the export start date is today instead of the > specified date. > > Do you know how I can obtain a correct HTML export ? > > I'm using version 0.14.5. I just tried with Planner 0.14.4, changing project start date to 10 days ago. With some test tasks, I get: Start: January 10, 2012 Finish: January 24, 2012 Report Date: January 20, 2012 The dates are correct. Can you tell us more precisely what you get? -- Alexandre Franke _______________________________________________ planner-list mailing list [email protected] http://mail.gnome.org/mailman/listinfo/planner-list