Re: Planner-list start date for HTML export

Alexandre Franke <[email protected]> Fri, 20 Jan 2012 16:14:25 +0100
Newsgroups gmane.comp.gnome.apps.planner.user
Message-ID <CAJ-e=JDF2AEFqPsRiyD847nUVncPn+Bu9SGav21Oooyw8ckPMg@mail.gmail.com>
2012/1/20 Jérôme VÉRITÉ <[email protected]>:
> Hi,

Bonjour,

> I try to export a project to the HTML view with a specified start date in
> the project properties but the export start date is today instead of the
> specified date.
>
> Do you know how I can obtain a correct HTML export ?
>
> I'm using version 0.14.5.

I just tried with Planner 0.14.4, changing project start date to 10
days ago. With some test tasks, I get:

Start: 	January 10, 2012
Finish: 	January 24, 2012
Report Date: 	January 20, 2012

The dates are correct. Can you tell us more precisely what you get?

-- 
Alexandre Franke