Re: Planner-list resources units definition

Alexandre Franke <[email protected]> Fri, 21 Dec 2012 11:46:23 +0100
Newsgroups gmane.comp.gnome.apps.planner.user
Message-ID <CAJ-e=JDq_5ffgrUeruYrX2E46eZ82mn3=BG5p04vFcRQrPHOFQ@mail.gmail.com>
Hi,

On Fri, Dec 21, 2012 at 8:31 AM, e-letter <[email protected]> wrote:
> What is the definition of the 'units' value within the 'resources'
> dialogue window when editing a task?

It's a percentage. If you have two resources allocated to a 2-day task
at 100%, it means both people will be working on it full-time and the
task will be done in one day. If you have one resource allocated to a
5-day task at 50%, the person will work on it half-time and the task
will be done in ten days.

--
Alexandre Franke