Re: Planner-list resources units definition
Alexandre Franke <[email protected]> Fri, 21 Dec 2012 11:46:23 +0100
| Newsgroups | gmane.comp.gnome.apps.planner.user |
|---|---|
| Message-ID | <CAJ-e=JDq_5ffgrUeruYrX2E46eZ82mn3=BG5p04vFcRQrPHOFQ@mail.gmail.com> |
Hi, On Fri, Dec 21, 2012 at 8:31 AM, e-letter <[email protected]> wrote: > What is the definition of the 'units' value within the 'resources' > dialogue window when editing a task? It's a percentage. If you have two resources allocated to a 2-day task at 100%, it means both people will be working on it full-time and the task will be done in one day. If you have one resource allocated to a 5-day task at 50%, the person will work on it half-time and the task will be done in ten days. -- Alexandre Franke