Planner-list Is duration calculated correctly?

"Randy Zagar" <[email protected]>
Newsgroups gmane.comp.gnome.apps.planner.user
Message-ID <[email protected]>
I hope this isn't a PBKAC error, but I'm having problems understanding how
Planner computes task duration.

I create three resourses: two are material (dedicated servers), one is work
(a developer), and I create a task that's suppose to take 5 days of work.  I
assign the developer to the task and add the two resources he needs to do
the work.  For some reason the duration is now 1d 5h.  I'm sorry, but the
computer can't do what the developer does.  IMHO, a "material" can't do
"work" so adding "material" to a task shouldn't change the duration.

If somebody can't explain why my thinking is bogus, then I think we have a
bug.

-RZ

p.s.  This is planner 0.14.2 (fedora 9)

_______________________________________________
Planner-list mailing list
[email protected]
http://mail.gnome.org/mailman/listinfo/planner-list
lmpx.com only provides a reader for public news (NNTP) servers. It is not affiliated with the servers or forums shown here and is not responsible for the content of articles, which is written by their respective authors.