[openi18n-im:01365] r12.4 and r12.2.1 schedule draft
Leon Ho <[email protected]> Fri, 13 May 2005 14:32:31 +1000
| Newsgroups | gmane.comp.internationalization.input-methods |
|---|---|
| Message-ID | <[email protected]> |
Hi all,
First, as we discussed in the debrief meeting, we may need improve on areas
like web content, community engaging and QA/rel-eng front, as I want to call
for participate on the following areas:
- feature/schedule tracker - Leon
- release engineering - Jens / [contributors?]
- QA - Lawrence / [contributors?]
- Community engagement organizer - [contributors?]
- web content organizer - [contributors?]
Next Releases:
--------------
Please give some thoughts on the QA and rel-eng schedule part.
r12.2.1
Code Freeze - Jun 21
QA Period - Jun 22-24
Release - Jun 28
r12.4
Feature Freeze - May 27
API/ABI Freeze - Jun 30
r12.3-beta1
r12.3-beta2
Code Freeze - Apr 29
r12.3-rc1
r12.3-rc2
QA Period - Aug 22-26
Release - Aug 31
Roadmap:
--------
As the debrief meeting decision, we are still sticking on the current roadmap
model to have 3 months schedule for r12.4.
: |
Jan : trunk
: |
Feb 12.1.2 |
|
Mar |
|
Apr 12.2 ----- trunk
: |
May : |
: |
Jun 12.2.1 |
|
Jul |
|
Aug 12.4 ---- trunk
: |
Sep : |
: |
Oct 12.4.1 |
|
Nov |
|
Dec 12.6 ----- trunk
: |
Let discuss among ourselves, we want to finalize this schedule by next
Wednesday.
Regards,
Leon