Re: monthly schedule

Dan Rollo <[email protected]>
Newsgroups gmane.comp.java.cruise-control.user
Message-ID <[email protected]>
The <schedule> tag is based on millis intervals, so you could use the 
number of millis in 30 days, but that would not ensure the build 
occurred the 1st of the month.

http://cruisecontrol.sourceforge.net/main/configxml.html#schedule

A workaround could be to use a <filesystem> modification set, and point 
it to one file that you will change only when you want to trigger a 
build. If you use something else (like cron) to "touch" that file on the 
1st of each month, it should work.

http://cruisecontrol.sourceforge.net/main/configxml.html#filesystem

Dan



> Date: Wed, 18 Aug 2010 09:07:37 -0400
> Subject: [Cruisecontrol-user] monthly schedule
> To:"[email protected]"
> 	<[email protected]>
>
> Can anyone help me with the best way to implement a schedule for a project that would only run on the 1st of every month?
>
>
> Thanks,
> Dana


------------------------------------------------------------------------------
This SF.net email is sponsored by 

Make an app they can't live without
Enter the BlackBerry Developer Challenge
http://p.sf.net/sfu/RIM-dev2dev
lmpx.com only provides a reader for public news (NNTP) servers. It is not affiliated with the servers or forums shown here and is not responsible for the content of articles, which is written by their respective authors.