Remaining Estimate field
| Newsgroups | gmane.comp.java.jira.user |
|---|---|
| Message-ID | <23782769.463361309332914185.JavaMail.j2ee_forums.atlassian.com@atlassian12.managed.contegix.com> |
Hi All i have added the time tracking field in my edit screen. One of the users after entering data in Original estimate field entered data in remaining estimate field also. After which he has logged effort using the log work feature. Now the time tracking graph in the view screen does not reflect the actual value. What can be done to resolve this. Also is there some way we can diable this field so that users can enter data in the original estimate field only. Thank you in advance Anupam -- Post by anupamsankar - online at: http://forums.atlassian.com/thread.jspa?forumID=46&threadID=55064 _______________________________________________ Jira-user mailing list [email protected] To unsubscribe or change your options visit this page: http://lists.atlassian.com/mailman/listinfo/jira-user