Burn Down Charts

"Harsh Khanna" <hkhanna-5ghuuo4IcBVWk0Htik3J/[email protected]> Tue, 4 Dec 2007 14:57:39 +0530
Newsgroups gmane.comp.java.xplanner.devel
Organization Gemstone Systems Pvt. Ltd.
Message-ID <004a01c83657$eae797c0$870a3c0a@pc35>
Hi

We're trying to use XPLanned standalone.

As it turns out we're entering data for a past iteration from an xls (where
else) into the Xplanner.

I explicitly ensured all time recorded dates were set to the day the actual
work was done.

I still do not see any burndown charts - just a dot on the curret day. The
iteration end date was set to greater than today.

Any helpful pointers?

Thanx
-Harsh



-------------------------------------------------------------------------