kplato; show actual planning
Thomas Zander <[email protected]> Wed, 25 Mar 2009 19:33:16 +0100
| Newsgroups | gmane.comp.kde.koffice |
|---|---|
| Organization | KDE |
| Message-ID | <[email protected]> |
I've been playing with KPlato from KOffice2.0 (thanks fly to Alexis) and there are 2 questions I have on its usage; * First is if I have a project. I added various tasks and made them into a scheduled list of items then I can calculate the schedule. It will schedule the tasks and put them on a timeline so I can see exactly when each tasks starts and ends. Now, if I then go and update each task as time goes by I end up with the actually taken time per task. This can be less than the planned time, or more. Question; how do I show the updated schedule with the new times ? Another Question; I think it would be useful to create more than one schedule with different parameters. For example I would have a schedule that is the pessimistic timeline and another that is the optimistic one. I can't seem to find out how to do that (it used to be possible AFAIK). Thanks for any help! -- Thomas Zander ____________________________________ koffice mailing list [email protected] To unsubscribe please visit: https://mail.kde.org/mailman/listinfo/koffice
signature.asc
(application/pgp-signature, 197 B)
-----BEGIN PGP SIGNATURE----- Version: GnuPG v1.4.9 (GNU/Linux) iEYEABECAAYFAknKeOwACgkQCojCW6H2z/Q3EwCfeD6iRGGO4HB3E3Ju/QllVOwb RUQAn1vk5LAr1sBehArVKSKhGYH5LdMM =7YTZ -----END PGP SIGNATURE-----