Re: kplato: Calculating schedule doesn't work
Vidar Langseid <[email protected]> Tue, 19 May 2009 09:56:42 +0200
| Newsgroups | gmane.comp.kde.koffice |
|---|---|
| Message-ID | <[email protected]> |
Hi On Monday 18 May 2009 02:47:22 pm Dag Andersen wrote: > Mandag 18 maj 2009 13:16:25 skrev Vidar Langseid: > > Hi > > > > On Monday 18 May 2009 Dag Andersen wrote > > > > >Hi Vidar. > > >Your resource refer to calendar 'vl' which doesn't define any working > > > hours at all. If you define some working hours, or use the 'Base' > > > calendar instead it should work. > > > > Thanx. That was one missing link. I had totally overlooked the view for > > specifying that. Your email got me on the right track. > > > > Fixing the working hours makes the warnings/errors in the log to > > disappear. However, my four tasks (task1.1, task2.1,task2.2 and task2.3 ) > > are still scheduled in parallel (meaning that "vl" would need to work > > 400% in order to comply with the suggested plan while the limit is set to > > 100%). In View->Resource Assignments it only shows 8h a day. > > It seems to work here. > Hmmm, did you create a new schedule or did you just recalculate the old > one? If you created a new, you'll have to select the correct schedule to > view in the View menu. (It should list all schedules you have calculated) > Also, the schedule name is shown in the status line (bottom right). I recalculated the old one. I also made a dependency between task2.1 and task2.2 just for fun. But task1.1, task2.1 and task2.3 is still scheduled in parallel (see attachment). > I know, this isn't fantastic, it's easy to forget/overlook, so I'm *very* > open for suggestions of how to improve this! I don't think this is that bad, but I do have a different suggestion: When you hit "calculate" button all trees in all views are collapsed. I suggest to add "collapse all" and "uncollapse all" buttons in all tree-views. The state of each tree-view should also not change when you press "calculate" button or do save/open. Best regards, Vidar > > > PS : Since you didn't CC me on the answer I had some problems answering > > to your email with correct reply-to headers, causing the threading to be > > wrong. I have now subscribed to the list so that shouldn't be a problem > > in the future. > > > > Best regards, > > Vidar > > > > On Monday 18 May 2009 10:37:07 am Vidar Langseid wrote: > > > Hi > > > > > > Sorry, but there must be something fundamental in kplato I have missed. > > > I hope someone might be able to help. > > > I have made one resource(person), one calendar and a few tasks which > > > are all assigned to the one resource. > > > > > > I then expect that when I hit the "Calculate" button that kplato would > > > schedule the tasks so that they don't overlap (the one resource I have > > > should only work 8 hours a day...). However this doesn't work. > > > > > > When I hit the "Calculate" button I instead get cryptic messages in the > > > log like: > > > "Could not match effort. Want 16h0m got 0h0m" > > > "Resource vl available from 05/18/09 12:00am to 05/18/11 04:00pm" > > > "Resource vl not available in interval: 05/18/09 12:00am to 05/18/09 > > > 04:00pm" All tasks is defined "As soon as possible", no fixed dates. > > > > > > Clicking on view->Resource assignments shows 0.0 in total for my > > > resource so there might some mapping between resource and tasks I have > > > missed ? > > > > > > I have attached my test project in the email( not sure it will get > > > through to the mailing list though) > > > > > > I am using KOffice 2.0RC-1 from Kubuntu/Jaunty > > > (KPlato v.0.6.99) > > > > > > Best regards, > > > Vidar -- [email protected] | eZ systems | ez.no ____________________________________ koffice mailing list [email protected] To unsubscribe please visit: https://mail.kde.org/mailman/listinfo/koffice
kplato_vltest.kplato
(application/x-vnd.kde.kplato, 5.4 KB) - not displayed