Re: kplato: Calculating schedule doesn't work

Dag Andersen <[email protected]> Fri, 22 May 2009 13:20:08 +0200
Newsgroups gmane.comp.kde.koffice
Message-ID <[email protected]>
Hi, All.
This was a real kplato bug in the rc1 release. It is definitly present in 
kubuntu/jaunty packages, and most likely in any other distrubution also. 
It will be fixed in the next release.

Thanks to Vidar for spotting it.

-- 
Mvh.
Dag Andersen

------------------------
Mandag 18 maj 2009 10:37:07 skrev Vidar Langseid:
> Hi
>
> Sorry, but there must be something fundamental in kplato I have missed. I
> hope someone might be able to help.
> I have made one resource(person), one calendar and a few tasks which are
> all assigned to the one resource.
>
> I then expect that when I hit the "Calculate" button that kplato would
> schedule the tasks so that they don't overlap (the one resource I have
> should only work 8 hours a day...). However this doesn't work.
>
> When I hit the "Calculate" button I instead get cryptic messages in the log
> like:
> "Could not  match effort. Want 16h0m got 0h0m"
> "Resource vl available from 05/18/09 12:00am to 05/18/11 04:00pm"
> "Resource vl not available in interval: 05/18/09 12:00am to 05/18/09
> 04:00pm" All tasks is defined "As soon as possible", no fixed dates.
>
> Clicking on view->Resource assignments shows 0.0 in total for my resource
> so there might some mapping between resource and tasks I have missed ?
>
> I have attached my test project in the email( not sure it will get through
> to the mailing list though)
>
> I am using KOffice 2.0RC-1 from Kubuntu/Jaunty
> (KPlato v.0.6.99)
>
> Best regards,
> Vidar