Re: request
Mark Tombs <[email protected]> Sun, 31 Oct 2004 20:02:08 +0100
| Newsgroups | gmane.comp.kde.kplato |
|---|---|
| Message-ID | <[email protected]> |
On Sunday 31 October 2004 13.14, Mark Tombs wrote: > On Sunday 31 October 2004 11.22, Dag Andersen wrote: > > On Fredag 29 oktober 2004 20:35, Mark Tombs wrote: > > > Hi list > > > > > > I have a request for kplato functionality. Can it please, please, > > > please not auto-schedule the way MS Project does, or at least make > > > it optional? Its the most annoying thing. If I have an > > > > I think optional. > > > > > over-allocation or whatever, I prefer to be told about it and > > > decide myself what to do, rather than have my tasks shifting all > > > over the place. > > > > To be able to find out if there is conflicts the project needs to be > > scheduled, no? > > Of course, but it doesn't need to be automatically scheduled for me. I am > capable of entering my own task durations (which doesn't have to be work * > resources, like MSProject insists.) I want to be in control of my project > plan, is all. I should be able to over-allocate resources if I want to :) > An auto-schedule function should definitely exist, but in my opinion it > should be something I request, then it happens, then my plan is left alone, > if you understand what I mean. > > > Hmm, maybe if we define a 'schedule only new task'-mode of calculation > > that effectively freezes existing tasks. > > So, if linked to existing tasks the new task will be scheduled in > > accordance with these but the old tasks will not be rescheduled. > > If there is enough float and resources it's ok, else conflicts are > > reported. > > What do say? > > > > > Don't know what the plans are re this, but thought I'd get in > > > early... > > > > > > thanks > > > > > > Mark > > > _______________________________________________ > > > kplato mailing list > > > [email protected] > > > https://mail.kde.org/mailman/listinfo/kplato > > _______________________________________________ > kplato mailing list > [email protected] > https://mail.kde.org/mailman/listinfo/kplato Some more observations on this. Having looked at the Task Properties dialog, I personally found it confusing, and I think this is because I am not used to MS Project. All of the settings and options there seem to assume that as soon as I change any values, all my tasks will be shifted about. I think the basic, fundamental thing that I don't agree with is that task duration is linked to estimated effort. I also don't think that changing one task should automagically change other tasks too. It seems to me that if you break the link between duration and estimates then a lot of the options in the task dialog go away, and even more go away if you don't auto-schedule. Lets say, for instance, that it works this way: 1. I enter my tasks with durations on them (no estimates yet though) 2. I set up the task dependencies. 3. I click the 'auto-schedule' button, tell it which date to start from (default from today) and bingo, all my tasks have start and end dates, and I have a project plan. Now all I need in a task dialog are task name, duration, start date, end date, and a check-box for start and end date saying if they are fixed or not. That way I can pin a task if I don't want it moved by the auto-schedule process. I've taken the liberty of knocking up a dialog. Of course, I can enter assignments with estimates on them, and the auto-schedule process will take those into account. I don't want to stir up a whole hornets nest here, it just seems a lot simpler this way... mark _______________________________________________ kplato mailing list [email protected] https://mail.kde.org/mailman/listinfo/kplato
marks-task-dialog.ui
(application/x-designer, 10.4 KB) - not displayed