Re: explenation from project managers please?
Chris H <[email protected]>
| Newsgroups | gmane.comp.kde.kplato |
|---|---|
| Message-ID | <[email protected]> |
On February 23, 2003 03:06 pm, Thomas Zander wrote: > Hi! > > I updates some stuff in kplato and we have a more user-friendly project > management dialog. > > I want some 'texts' from the people that know most about project plannings > to finish stuff. Its in CVS, just start it up and you will see why I ask. > > - what is the influence of scheduling type on a project. (small 7 word > sentence please). - please give me a 3 sentence explenation for each of the > following scheduling types: IMHO only - ASAP (as soon as possible) - ALAP (as late as possible) - Start not earier then ( project element cannot start until a specified date: typically dependent on completion of another task) -Finish not later then (time dependent completion date: ie: schedule dependant) - Must start on (time dependant start date -schedule dependant) Hope that help, of course its only my interpretation. /ch