Re: explenation from project managers please?
John Lamb <[email protected]>
| Newsgroups | gmane.comp.kde.kplato |
|---|---|
| Message-ID | <[email protected]> |
Thomas Zander wrote: > so two groups of radiobuttons: > > Project scheduling: (won't effect start/end time) > o ASAP > o ALAP > Project start/end > o Start not earier then > o Finish not later then > o Must start on > > Right? These look sensible. ASAP and ALAP don't affect pert/cpm because they are essentially resource allocation problems. ASAP make sense if you want to avoid the risk of overrunning on non-critical activities. ALAP makes sense if the resources are expensive and hired/rented at the point of need (e.g. hiring a large crane for construction) because that delays capital expenditure. I guess project start/end time is to allow the possibility that the project itself may have some slack. It certainly makes sense to build that in. -- JDL