Re: setting up a calendar
Adam Hardy <[email protected]> Tue, 12 Dec 2006 00:37:01 +0000
| Newsgroups | gmane.comp.kde.kplato |
|---|---|
| Message-ID | <[email protected]> |
Dag Andersen on 25/11/06 15:34, wrote: > Fredag 24 november 2006 02:12 skrev Adam Hardy: > (...) >> I have 4 working days in my week. Three have working intervals with 2 >> hours. The fourth has a working interval of 3 hours. >> >> Now when I enter the effort required on a task, I put in 5 hours, for >> example. Kplato then recalculates this into 2 days and 1 hour. I guess this >> is because I have set the Standard Worktime for a day to be 2 hours. Is >> that true? >> >> But that is only roughly correct, because really my average working day is >> 2.25 hours. >> > It uses the "Hour pr day" field (above) for this calculation. >> >> I would prefer to keep my task effort estimates as hours, instead of >> allowing kplato to recalculate them into days. Is there a way of doing >> this? >> > No, not atm. This widget has to be rewritten, though, due to problems with > layout and navigation, so maybe in the future (koffice 2.0). I am curious about this situation where kplato rewrites 'hours effort' in the calendar into days where it can, depending on the standard worktime. Why is there a dependency on standard worktime? Especially in my project, it just doesn't make sense because I intend to vary the intervals heavily and don't have any concept of standard worktime. Particularly my attempts to work out what kplato is doing are slightly confusing. I added a task for 2 hours. I also have 2 hours entered as the standard worktime number of hours per day. The task settings effort estimate changed my 2 hours to 1 day. So to check what happens, I increased the number of hours on the day for that task from 2 up to 8, expecting to see the task expand as the day expands, but it doesn't. Does the task setting somehow invisibly remember that I entered 2 hours and not 1 day? Regards Adam