We want to display three curves to answer this need :

" The best charting available is
to display Budgeted Cost of Work Scheduled vs. Budgeted Cost of Work
Performed (Schedule Variance); and Budgeted Cost of Work Performed vs.
Actual Cost of Work Performed (Cost Variance)."

On the X-coordinate : the current duration of the project
On the Y-coordinate : the percentage of the budgeted cost of work
Scheduled...etc

It will be integer points that we need to join with graphical curves.
A simple chart with some colours ;)


2007/1/18, Thomas Zander <[email protected]>:
> On Wednesday 17 January 2007 15:27, Fr=E9d=E9ric Lambert wrote:
> > We are working  on the possibility to display 3 curves like mentionned =
in
> > previous post.
>
> There still is some confusion around this issue, and that stems mostly fr=
om
> the question if kchart is the right solution.
>
> Could you explain what you need this for?
> What kind of data (examples please) do you want to display on screen?
>
> Thanks!
> --