Re: feature request

Dag Andersen <[email protected]> Mon, 21 May 2007 20:57:08 +0200
Newsgroups gmane.comp.kde.kplato
Message-ID <[email protected]>
Onsdag 16 maj 2007 21:23 skrev mimoune djouallah:
> hello
>
> i am wondering if you will add the ability to assign a budget quantity of
> resource to task, for example it is simpler to say i have a budget quantity
> of resource bull 80 hour per day, thus 10 bull ( assuming the limit of this
> resource is 8h ) then to say i have bull1 , bull2 ..... bull10
> thanks
Hmmm, I had the intention to add the possibility to assign a quantity of 
resource units to a task and let the scheduling routines select which 
resource(s) to assign to the task. (Not at the top of my list, though)

Another possiblity I had in mind was to set a limit for a resource (possible 
allready) of say 800% and then allocate just a part (not possible yet) to a 
task.

I don't know if either covers your needs, but anyway, could you open a bug 
(wish) report for this?
> ps: sorry for my English, that's the best i could do.
No problem :)
-- 
Mvh
Dag Andersen